To configure the Gantt chart switch to the edit page mode and click “Configure Virto Gantts”.

configure_the_gantt_chart_1

Or use the same button on the page with data source list.

configure_the_gantt_chart_2

On the page with available Gantts you can edit/delete existing configured Gantts or add a new Gantt.

configure_the_gantt_chart_3

Click “Add new Gantt” to add a new Gantt chart.

configure_the_gantt_chart_4

Required fields are marked with “*” symbol.

Type the Gantt name. Then click “Add new source” button to add at least one data source to the Gantt.

configure_the_gantt_chart_5

Every data source has its own options. You can tick off the checkbox “Show in Virto SharePoint Gantt“. This data source will be unavailable for displaying (will be saved without publishing). Also, you can add data source with read only permission, i.e. user will not be able to create/modify tasks in the Gantt Chart Web Part for the data source.

configure_the_gantt_chart_6

Click “Save” button. You can add other data sources to this Gantt as well.

Then set height of Gantt in pixels if you want to limit size of Virto Gantt Chart Web Part displayed on site. Default height value is 800px, default width proportion is 100%.

configure_the_gantt_chart_7

Choose the default time scale (for example, days, weeks, months, and year).

configure_the_gantt_chart_8

Tick the checkbox “Use SharePoint form for editing task” to display default SharePoint form for task editing. You can also allow opening the SP form as a full-size page.

configure_the_gantt_chart_9

The “Enable export to PDF” feature allows you to save your Gantt chart as PDF.

configure_the_gantt_chart_10

This option adds the button on the Gantt header; the PDF file with current Gantt table view will be downloaded automatically after you click this button.

configure_the_gantt_chart_11

The next option allows you to show summary tasks collapsed by default.

The Auto schedule feature helps to manage successor and predecessor tasks. It protects from cases when a successor task starts before the predecessor.

configure_the_gantt_chart_12

Click “Save” to complete the new Gantt adding. The same way you can edit an existing Gantt.